Differences
This shows you the differences between two versions of the page.
| Both sides previous revisionPrevious revisionNext revision | Previous revision | ||
| report [2017/06/27 11:44] – [8.2 Future Development] team1 | report [2017/06/27 19:01] (current) – team1 | ||
|---|---|---|---|
| Line 149: | Line 149: | ||
| ==== 1.7 Project Planning ==== | ==== 1.7 Project Planning ==== | ||
| - | Every project needed to be planned carefully because a project plan gave an overview of all the tasks and deliverables that needed | + | Every project needed to be planned carefully because a project plan gives an overview of all the tasks and deliverables that need to be completed. Having a good project plan and following it well allowed the smooth running of the project, and kept the project running on schedule. Table {{ref> |
| <WRAP centeralign> | <WRAP centeralign> | ||
| <table tpjctpn> | <table tpjctpn> | ||
| Line 1324: | Line 1324: | ||
| ==== 7.3 Architecture ==== | ==== 7.3 Architecture ==== | ||
| - | ==== 7.3.1 First Structural Drawings | + | === 7.3.1 First Structural Drawings === |
| Figures {{ref> | Figures {{ref> | ||
| Line 1343: | Line 1343: | ||
| </ | </ | ||
| - | ==== 7.3.2 Cardboard Model ==== | + | === 7.3.2 Cardboard Model === |
| To begin with the architecture of the prototype, a cardboard model was made as a first approach to find out the optimal dimensions and opening system of the " | To begin with the architecture of the prototype, a cardboard model was made as a first approach to find out the optimal dimensions and opening system of the " | ||
| Line 1368: | Line 1368: | ||
| - | ==== 7.3.3 Initial 3D Model ==== | + | === 7.3.3 Initial 3D Model === |
| The Team created some initial three-dimensional (3D) models to see how the product would look like at the end of the project. | The Team created some initial three-dimensional (3D) models to see how the product would look like at the end of the project. | ||
| Line 1426: | Line 1426: | ||
| </ | </ | ||
| - | ==== 7.3.4 Final Structural Drawings | + | === 7.3.4 Final Structural Drawings === |
| The Team had to do some brainstorming in order to fix the flaws found in the first design. The original pivoting opening system was not very likely to be long lasting, and therefore unsustainable. In order to keep the cover removal simple, the group decided not to host the technologies inside the cover and add a chamfer instead for that purpose. These changes in the product (see Figure {{ref> | The Team had to do some brainstorming in order to fix the flaws found in the first design. The original pivoting opening system was not very likely to be long lasting, and therefore unsustainable. In order to keep the cover removal simple, the group decided not to host the technologies inside the cover and add a chamfer instead for that purpose. These changes in the product (see Figure {{ref> | ||
| Line 1437: | Line 1437: | ||
| </ | </ | ||
| - | ==== 7.3.5 Final 3D Model ==== | + | === 7.3.5 Final 3D Model === |
| In this sub-section, | In this sub-section, | ||
| Line 1483: | Line 1483: | ||
| </ | </ | ||
| - | ==== 7.3.6 Technical Drawings | + | === 7.3.6 Technical Drawings === |
| These technical drawings were made from the 3D model in Solidworks. These drawings are used as base for the making of the prototype. First of all there is an overview drawing of all components and the quantity is indicated on the bill of materials (see Figure {{ref> | These technical drawings were made from the 3D model in Solidworks. These drawings are used as base for the making of the prototype. First of all there is an overview drawing of all components and the quantity is indicated on the bill of materials (see Figure {{ref> | ||
| Line 1799: | Line 1799: | ||
| * The fan is represented by a 12 V motor. | * The fan is represented by a 12 V motor. | ||
| - | * Both LED modules are represented by 4500 LED lighting. | + | * Both LED modules are represented by LED lighting. |
| * The mains supplying a current of 12 V is represented by the battery of 9 V. | * The mains supplying a current of 12 V is represented by the battery of 9 V. | ||
| * To finish the Nokia 5110 LCD screen is symbolized by the Nokia 6100 screen. | * To finish the Nokia 5110 LCD screen is symbolized by the Nokia 6100 screen. | ||
| Line 1819: | Line 1819: | ||
| ==== 7.9 Tests and Results ==== | ==== 7.9 Tests and Results ==== | ||
| - | In this Section, the Team explains all tests performed and presents its results. | + | In this Section, the Team explains all tests (See section [[report# |
| + | |||
| + | The Team performed all the tests they thought that were necessary in the beginning. While developing the product they also decided to perform the soil tests to find the best way to keep the soil moist. | ||
| === 7.9.1 Electronics Tests === | === 7.9.1 Electronics Tests === | ||
| Line 1829: | Line 1831: | ||
| The temperature and humidity sensor measured the temperature and the humidity in the terrarium. The expected temperature range is between 15 °C and 25 °C. | The temperature and humidity sensor measured the temperature and the humidity in the terrarium. The expected temperature range is between 15 °C and 25 °C. | ||
| - | As defined in the paragraph | + | As defined in section [[report# |
| First of all, the Team wrote a program to control the following system (see Figure {{ref> | First of all, the Team wrote a program to control the following system (see Figure {{ref> | ||